December 2009 -
The electrical installation is complete. We are waiting for the final township inspection at which time engineering can move into the new storage
facility.
November 2009 -
Electrical work moving along on this project. Contractor will be back to insulate the building. Concrete pad being poured from shed to Frey Hall.
October 2009 -
Outside/inside skin and doors have been installed. Electrical grading and concrete to be completed in next two weeks.
September 2009 -
The engineering department has required more storage due to the addition of new programs. An area behind Frey Hall has been designated for a new storage building. The building will be 33 ft. wide by 30 ft. deep and will have pole building construction. This building will allow storage of equipment that is taken up much needed space.
|
|
|
|
|
|